Overview

  • Full CAT A building refurbishment
  • Newly configured reception
  • New high performance floor to ceiling double glazing throughout
  • Exposed styles services incorporating LG7 compliant LED lighting and new heating and cooling systems
  • Occupancy density 1:10 sqm
  • Toilet accommodation is designed to 1:8 sqm
  • Ventilation is designed to 1:8 sqm (with capacity to be modified to 1:6 sqm)
  • Secure fob access entrance

Parking

  • 18 secure bicycle storage
  • 22 on-site car parking spaces
  • 3 accessible car parking space

Mechanical Services

  • New mechanical installations throughout
  • New efficient VRF heating and cooling system via air-sourced heat pump
  • Office internal design conditions
    • 24 C +/- 2 C (Summer)
    • 21 C +/- 2 C (Winter)
  • Building energy management system (BEMS)

Electrical Services

  • New electrical installations throughout
  • LG7 compliant lighting (300-500 lux target)
  • Digital lighting control system
  • PIR lighting throughout the office and core with daylight sensors at office perimeters

Lifts

  • 4no. x new 8 person passenger lifts
  • Minimum 2.0 mps passenger lift speed

WCs and Showers

  • Male and female WCs accessible from each floor (excluding basement) South wing has unisex superloos on each floor. North wing has half-landing toilets, alternate male and female
  • Ambulant Disabled WC on each floor (excluding basement)
  • Full DDA facilities are located at ground floor (2no.) and at 7th floor (1no.)
  • Basement changing room with 3no. shower rooms and 18 lockers

Floor and Ceilings

  • Fully accessible raised access floor set 90mm from the top of the structural slab
  • Floor to ceiling heights between 2460-2900mm (to underside of beams)